How long does a kitchen renovation take?

For a kitchen renovation, allow approximately 4–6 weeks of construction for a kitchen refresh, 6–10 weeks for a full remodel within the room and 8–12 weeks for structural or open-plan work. Design, engineering, permits and ordering bring the overall project to roughly 2–5 months. A smaller finish-only update can differ. We agree the schedule for your scope and keep you informed as decisions, lead times, inspections or concealed conditions affect it.